Interstate pipelines operate under federal rules that require open access and public information. One result is the stream of pipeline notices that tell shippers about outages, constraints and operating conditions, the same notices NatGasPipe collects in one place.

Who regulates what

RegulatorOversees
FERC (Federal Energy Regulatory Commission)Interstate pipeline rates, terms of service, open access, new interstate pipelines and LNG terminals, and market manipulation rules
PHMSA (U.S. DOT)Pipeline safety: design, inspection, integrity management and operator qualification
State public utility commissionsLocal distribution company rates and service, and intrastate pipelines (in Texas, the Railroad Commission)
U.S. Department of EnergyAuthorizations to export and import natural gas, including LNG
CFTCFutures and derivatives markets, such as NYMEX Henry Hub

The key laws and orders

Tariffs and informational postings

Each interstate pipeline's tariff is its FERC-approved rulebook: services, rates, fuel, scheduling priority, imbalance penalties and operating conditions. Changing it requires a filing at FERC.

Under FERC regulations and NAESB standards, pipelines must publish informational postings on a public website, sometimes called the EBB or infopost. Required postings include:

Types of pipeline notices

CategoryWhat it meansExamples
CriticalAffects scheduling or could result in penalties. Shippers may need to act.OFOs, force majeure, capacity cuts, imbalance warnings, critical days, pressure problems
Non-criticalInformational, with no immediate operational action requiredRate and fuel changes, tariff filings, posting updates, holiday schedules, capacity release postings
Planned service outageScheduled maintenance that affects capacityCompressor maintenance, pipeline inspections (pigging), hydrostatic tests, tie-ins for new projects

Notices have a posted time, an effective time, and often an end time. A notice may supersede an earlier one, which happens when an outage is extended or a restriction is lifted. NatGasPipe shows current notices: those with no end date, or an end date that hasn't passed yet.

Operational flow orders and force majeure

Operational flow orders (OFOs)

An OFO is an order from the pipeline requiring shippers to take action to protect system integrity, usually to keep their receipts and deliveries in balance within a tight tolerance. OFOs often come with steep penalties for non-compliance and are common during extreme cold or heat. Pipelines may use related terms such as "critical day", "strained operating condition", or "system management order".

Force majeure

Force majeure is an unplanned event outside the pipeline's control, such as a pipe rupture, equipment failure, hurricane or other emergency, that forces capacity reductions. It's one of the most market-moving types of notice, because firm service may be cut and basis prices can jump.

How to read a notice quickly

  1. Category and type: is it critical, or a planned outage?
  2. Location: which segment, compressor station or meter is affected? Check the map.
  3. Capacity impact: how much is the reduction, in Dth/d or as a percentage, and which services will be cut? Interruptible and secondary-firm are usually cut first.
  4. Timing: the effective and end dates, in Central time.
  5. Action required: imbalance tolerances, OFO conditions, or deadlines for nomination changes.
Browse every current notice in one list on the Notices page, or see them by pipeline on the live map. Always confirm details on the pipeline's own informational postings before acting.
Key takeaways
  • FERC regulates interstate pipelines under the Natural Gas Act. PHMSA regulates safety.
  • Pipelines must post notices, capacity and tariffs publicly.
  • There are three notice categories: critical, non-critical and planned service outage.
  • OFOs and force majeure are the notices most likely to affect your gas and prices.

Key terms

FERC
Federal Energy Regulatory Commission.
Natural Gas Act
The 1938 law under which FERC regulates interstate pipelines.
Order 636
The 1992 FERC rule creating open-access transportation and capacity release.
Tariff
A pipeline's FERC-approved rules and rates.
Informational postings (EBB)
The pipeline's public website for notices, capacity and other required information.
Critical notice
A notice that may affect scheduling or bring penalties.
Planned service outage
Scheduled maintenance that reduces capacity.
OFO
Operational flow order: a required action to protect the system.
Force majeure
An unplanned event outside the pipeline's control that limits service.
Supersede