Every day, thousands of shippers tell pipelines how much gas they want moved, from where and to where. The pipelines confirm it with the parties upstream and downstream, then schedule it. These rules are standardized across North America by NAESB, the North American Energy Standards Board, and adopted by FERC.
The gas day
The industry's gas day runs from 9:00 a.m. to 9:00 a.m. Central Time, not midnight to midnight. A "flow date" of March 5 means gas flowing from 9 a.m. CT on March 5 to 9 a.m. CT on March 6. All times on NatGasPipe are U.S. Central.
Gas is assumed to flow at an even rate across the 24 hours, which is the basis of the EPSQ rules for intraday changes.
Nomination cycles
A nomination ("nom") is a shipper's request to move a quantity of gas on a given day. There are five standard cycles: two before the gas day starts and three intraday.
| Cycle | Nomination deadline (CT) | Gas starts flowing | Can bump interruptible? |
|---|---|---|---|
| Timely | 1:00 p.m. the day before | 9:00 a.m. (start of gas day) | Yes |
| Evening | 6:00 p.m. the day before | 9:00 a.m. (start of gas day) | Yes |
| Intraday 1 (ID1) | 10:00 a.m. on the gas day | 2:00 p.m. | Yes |
| Intraday 2 (ID2) | 2:30 p.m. | 6:00 p.m. | Yes |
| Intraday 3 (ID3) | 7:00 p.m. | 10:00 p.m. | No |
Most gas is nominated in the Timely cycle. Later cycles let shippers adjust as weather, power demand or plant conditions change. Some pipelines offer extra cycles or have their own variations, so check the tariff.
From nomination to scheduled quantity
- Nominate: the shipper submits volumes, receipt and delivery points, the contract, and the upstream and downstream parties, usually on the pipeline's electronic bulletin board.
- Confirm: the pipeline checks with the operator on each side of the transaction, for example the upstream pipeline or the producer's meter. If they confirm different volumes, the lesser quantity usually wins.
- Schedule: the pipeline runs its capacity checks. If a segment or point is overbooked, it cuts volumes by priority.
- Flow and measure: gas flows, and meters record what actually moved.
- Allocate: actual measured volumes are assigned back to shippers, often by a predetermined allocation (PDA) method agreed in advance.
Priority and bumping
When requests exceed capacity, pipelines schedule in priority order. Each tariff sets its own exact order, but it typically runs:
- Firm service using primary points
- Firm service using secondary points within the contract path
- Firm service using secondary points outside the path
- Interruptible service, usually ranked by the rate paid
Bumping is when a higher-priority firm nomination in a later cycle displaces interruptible gas that was already scheduled. It's allowed in the Timely, Evening, ID1 and ID2 cycles, but not in ID3, so interruptible shippers get some certainty late in the day.
EPSQ: limits on cutting back intraday
By the time an intraday cycle takes effect, part of the day's gas has already flowed. You can't reduce your nomination below what has already moved. That floor is the elapsed prorated scheduled quantity (EPSQ). For example, ID1 starts at 2 p.m., 5 hours into the gas day, so at least 5/24 of the previously scheduled quantity has already flowed.
Imbalances
An imbalance is the difference between what was scheduled and what actually flowed, or between the gas a shipper put in and took out. Pipelines need these to stay small to keep the system safe:
- Tolerances: small daily or monthly imbalances are usually allowed without penalty.
- Cash-out: monthly imbalances outside tolerance are settled in cash, often at index-based prices with escalating penalties.
- Make-up: some pipelines let shippers fix imbalances by shipping extra gas, or less, later on.
- OBA (operational balancing agreement): an agreement between interconnecting operators to handle differences at a point between themselves.
When the system is stressed, pipelines tighten the rules with operational flow orders (OFOs) and imbalance warnings, which come out as critical notices.
- The gas day runs 9 a.m. to 9 a.m. Central.
- There are five standard cycles: Timely, Evening, ID1, ID2 and ID3.
- Nominate, then confirm, then schedule, flow and allocate.
- Firm primary beats secondary, which beats interruptible. Bumping is allowed up through ID2.
- Intraday cuts are limited by EPSQ. Imbalances outside tolerance get cashed out or penalized.
Key terms
- Gas day
- 9:00 a.m. to 9:00 a.m. Central Time.
- Nomination
- A shipper's request to move a quantity of gas on a given day.
- Confirmation
- Verification of a nomination with the upstream and downstream operators.
- Scheduled quantity
- The volume the pipeline has accepted to flow.
- Bumping
- Firm nominations displacing scheduled interruptible gas.
- EPSQ
- Elapsed prorated scheduled quantity: the floor for intraday reductions.
- Allocation / PDA
- How measured volumes are assigned to shippers; PDA is a predetermined allocation method.
- Imbalance
- The difference between scheduled or received gas and actual deliveries.
- Cash-out
- Settling an imbalance in money rather than gas.
- OBA
- Operational balancing agreement between interconnected operators.
- NAESB
- North American Energy Standards Board, which writes the gas-industry business standards.